Prescribed Building Professionals (PBP) and Prescribed Registered Contractors (PRC)

7 days before commencement of works

  1. Submit notification of works
    MW01  )
  2. Submit Prescribed plans, details of works, and other documents (e.g. Site supervision plan)
  3. Submit photos

Issue acknowledgement letter *

Buildings Department will issue acknowledgement letter for notification of commencement of works with submission no. , after preliminary checking of the information submitted.

Carrying out of the works

Within 14 days after completion of works

  1. Submit a Certificate of completion of works
    MW02  )
  2. Submit revised plans, details of the works showing the minor deviations and other relevant documents (if any)
  3. Submit photos

Issue acknowledgement letter *

Buildings Department will issue acknowledgement letter for certification of completion of works after preliminary checking of the information submitted.